نیپرا کے پروسیومر ریگولیشنز 2026 کے بعد نیٹ میٹرنگ کی جگہ نیٹ بلنگ آ گئی ہے۔ نئے سولر صارفین کو گرڈ کو دی گئی بجلی کا تقریباً 10 سے 11 روپے فی یونٹ ملتا ہے، اس لیے سسٹم اپنے دن کے استعمال کے مطابق لگوائیں۔
After installing solar, many people get a green meter so they can sell surplus daytime electricity to the grid. But the rules changed in 2026 — net metering has been replaced by net billing. This guide explains the green meter, what the new rules mean for you, and the full process in plain language.
What is a green meter?
A green meter is a bi-directional meter that records two things separately:
- Import: electricity you took from the grid
- Export: solar electricity you sent to the grid
A normal meter only records import. Without a green meter, any surplus solar electricity that flows into the grid earns you no credit.
From net metering to net billing — what changed?
NEPRA notified the Prosumer Regulations 2026, effective 9 February 2026, replacing the 2015 net metering regulations.
| Item | Old net metering | New net billing (2026) |
|---|---|---|
| Accounting | Unit for unit | Import and export calculated separately |
| Export rate | About Rs 26 per unit | About Rs 10–11 per unit (national average energy price) |
| Import rate | On net units | Full consumer tariff + taxes |
| Contract | 7 years | 5 years |
Following the government’s direction, existing (already registered) consumers keep their old arrangement until their contracts end, while new solar users are on net billing. A processing fee of Rs 1,000 per kW now applies to every new solar connection.
What this means for you
If you sell 1 unit to the grid for Rs 11 and buy the same unit back at night for Rs 40+, selling is not profitable. So now:
- Size your system to your own daytime use.
- Consider a battery for night-time use.
- Run heavy appliances (pump, iron, washing machine, AC) during the day.
Right size for your units: Solar Calculator. Costs: 5 kW and 10 kW solar system price.
How to get a green meter (step by step)
- Choose an installer: one registered with AEDB/your DISCO who prepares the net billing file for you.
- Application: submit a net billing application to your DISCO (LESCO, MEPCO, FESCO, etc.). Companies are required to provide application documents free of charge and process them within set timelines.
- Documents: CNIC, electricity bill (in your name, or with an NOC), system technical details (panel and inverter models and certificates), and the processing fee receipt.
- Technical survey and approval: the DISCO inspects the site, and NEPRA concurrence is processed.
- Agreement: after approval, a 5-year agreement between you and the DISCO.
- Meter installation: the green (bi-directional) meter is installed, and from the next bill import and export are shown separately.
Timelines and procedures can vary between companies — get the latest checklist from your DISCO’s customer service centre before applying.
How to read a green meter bill
The bill shows import units, export units and their amounts separately. Import units are billed like a normal bill with slabs, fixed charges, FPA and taxes (see: bill charges explained), while export units are credited at the lower rate.
Frequently asked questions
Is a green meter still worth it?
If you regularly have surplus daytime electricity, yes — you earn some credit. But installing a big system just to sell is no longer as profitable. For most homes, a hybrid inverter with the right system size is the better choice.
My net metering was installed in 2025 — what changes?
Existing registered consumers keep the old arrangement for the term of their agreement. When it expires, the new rules apply. Check your agreement date.
Can I install solar without a green meter?
Yes. Set your hybrid or on-grid inverter to “zero export” and use solar only for your own consumption. No electricity goes to the grid, so you don’t need a green meter.