نیا بجلی کنکشن اب ای این سی پورٹل پر آن لائن اپلائی ہوتا ہے۔ ضروری کاغذات، ڈیمانڈ نوٹس، نام کی تبدیلی اور لوڈ بڑھانے کا پورا طریقہ نیچے دیکھیں۔
A new house, shop or separate portion — all need a new electricity connection, and you can now apply online. Pakistan’s government power companies (LESCO, MEPCO, FESCO, GEPCO, PESCO, HESCO and others) share one system called ENC (Electricity New Connection). This guide covers a new connection, name change and load increase.
New connection — 5 steps
- Online application: on the ENC portal choose “Apply”, select your company (e.g. LESCO) and fill in the form — name, CNIC, address, connection type (home/commercial) and required load.
- Tracking ID: you get a tracking ID as soon as you submit — keep it safe; you’ll use it to check status and print the demand notice.
- Documents: submit documents with the application or at the sub-division office (list below).
- Survey and demand notice: the company surveys the site and issues a demand notice listing the cost of the meter, cable, security deposit, etc. Print it from the portal and pay at the designated bank.
- Meter installation: after you upload/submit the paid demand notice receipt, the meter is installed and bills start the following month.
IESCO has its own ENC portal; the other companies use the shared ENC system. K-Electric (Karachi) has a separate process.
Required documents
- Applicant’s CNIC (copy)
- Proof of property — registry, mutation (intiqal), allotment letter, or if renting, the owner’s NOC and CNIC
- A neighbour’s electricity bill (to identify the nearby connection)
- Wiring contractor’s test report
- In some companies, an affidavit on stamp paper
- For commercial connections, proof of business
Checklists can differ slightly between companies — get the latest list from the portal or your sub-division before applying.
How long does it take?
If your documents are complete and the transformer has capacity, the meter is usually installed within a few weeks after the demand notice is paid. If a new pole or transformer is needed, it takes longer. Check progress on the portal with your tracking ID.
How to change the name on an electricity bill
Bought a house and the bill is still in the old owner’s name? Changing the name is important — otherwise net billing, load changes or complaints become difficult.
- On the ENC portal choose “Change of Name / Tariff / Load”, or visit your sub-division office.
- Documents: new owner’s CNIC, property registry/mutation, the latest paid bill, and if required the previous owner’s NOC/CNIC.
- Pay the small fee demand notice.
- After approval the new name appears on the next bill — the reference number stays the same.
Important: clear all arrears before applying for a name change, or the application may be held up.
Increasing or reducing your load
If you need more load for ACs or new appliances, apply for “Change of Load” on ENC. Since 2026 fixed charges are based on load, so only take the load you need. A load above 5 kW gets a TOU meter — details: Three phase and TOU meter.
Your first bill on a new connection
Because there is no 6-month history yet, your category is decided under the company’s rules. Keep an eye on the 200-unit line — 200 vs 201 units. When the bill arrives: duplicate bill online.
Frequently asked questions
Is a new connection completely online?
The application, tracking and demand notice printing are online. Document verification, the survey and meter installation are done by the company’s staff.
I lost my demand notice — what now?
Enter your tracking ID on the ENC portal and print it again.
Do I need an agent or a “fast service”?
No. The whole process runs through the company’s official system. Don’t pay anyone extra, and get a bank receipt for every payment. For complaints: complaint numbers.